BIM and LOD rules

What we ask of any designer or builder who works on an HFL campus, and how to learn it.

levels

Levels of development

A level of development says how much a model element can be trusted for a decision. Use the least detail that supports the decision.

Levels of development
LevelNameWhat the element carriesCampus use
LOD 100ConceptA symbol or a simple mass. Area and rough height only.Site study: where do the modules fit, how many learners can we host.
LOD 200GenericApproximate size, shape, position and a generic type. Uses our element code.Layout and space programme. Check seat counts and routes.
LOD 300PreciseExact size, shape and position, with the main material and fire rating.Design approval and quantities for a first budget.
LOD 350CoordinatedAdds connections and fixings, so other trades can check clashes.Coordination between structure, services and interior.
LOD 400FabricationEnough detail for the factory to make it and the site to assemble it.Module shop drawings, stair and glass-wall fabrication.
LOD 500As builtWhat was really built, checked on site.Handover to the facility team and the digital twin.

information

Information every element carries

  • Element code and name from our library (for example CS-IN-01).
  • Fire rating, acoustic rating and finish.
  • Supplier-neutral specification text: describe the performance, never a brand.
  • Maintenance interval and expected life.
  • Certificates held, and where the file is stored.

rules

Seven model rules

  • Every model uses open file formats so any team can open it. Native files stay inside the team that made them.
  • Names follow one pattern: campus, building, level, discipline, element code. Example: C01-B1-L2-ARC-CS-IN-01.
  • One shared model environment holds the current, approved and archived versions. Nobody sends models by chat or mail.
  • Each element lists a responsible author and the level of development it reached.
  • Supplier and maker names never go into the model, the drawings, the schedules or the file names. A neutral description and our code are used instead.
  • Quantities come from the model. A quantity that cannot be traced to the model is not accepted.
  • Handover includes the as-built model, the element list, the certificate list and a maintenance plan.